Zimbabwe Power
Company
April 26, 2012
It is with regret that
I advise of the fact that we (Zimbabwe Power Company) lost the four
producing units at Hwange Power Station yesterday afternoon (Wednesday
25th April). One unit was brought back onto the grid last night
and we hope to bring a second, larger unit, back around 4am tomorrow
(Friday 26th April). Repair on the third unit is scheduled for completion
such that it will be 'returned to service' on Saturday morning.
Two phase one (smaller)
units are having their rotors re-wired in South Africa - this is
major work.
Kariba has five units
on line with the sixth due back on the grid in mid-May after routine,
but critical, maintenance ahead of winter.
The Hwange and
Kariba expansion plans remain on program at this time. The tenders
are out and close in June. This will be followed by 2 three-month
periods for tender review and finalisation of funding/award. Thereafter
construction will take between three to four years (2016-17).
R. Maasdorp
Chairman ZPC